Concrete Manual Tests: Verification of Water in Fresh Concrete by Use of a Microwave Oven Mobile App

DOT has incorporated the use of AASHTO TP23-93 to verify the Contractor’s water in concrete pavements. This test uses a microwave oven to drive the water out of fresh concrete. Mn/DOT has an incentive/disincentive program for the water-cementitious (w/c) ratio. This incentive is based on the Contractor’s actual batch weights and is verified using the microwave. Use the Concrete Manual Tests: Verification of Water in Fresh Concrete by Use of a Microwave Oven mobile app to complete this verification process.

  • Lendlease
  • The Cooperative
  • PG&E
  • oxy
  • Red Bull
  • Mirvac

Want to learn more about GoCanvas?

Request a Demo

Take a peek inside the Concrete Manual Tests: Verification of Water in Fresh Concrete by Use of a Microwave Oven Mobile App

Included Features

Our App Builder gives you the power to easily add and remove the ones you want. {{controller.show_all ? 'See included features.' : 'See more features.'}}

  • {{data.title}}

Included Fields

Customize to add, remove, or edit any of the fields below.

  • Ico statictext

    VERIFICATION OF WATER IN FRESH CONCRETE BY USE OF A MICROWAVE OVEN

  • Ico statictext

    Mn/DOT has incorporated the use of AASHTO TP23-93 to verify the Contractor’s water in concrete pa...

  • Ico statictext

    Knowing the weight of the fresh concrete and the weight of the dried concrete, the total water co...

  • Ico statictext

    There are many variables in this procedure.

  • Ico statictext

    Moisture tests and microwave oven testing are performed by the Agency.

  • Ico statictext

    A.

  • Ico statictext

    B.

  • Ico checkbox

    For determination of water/cementitious ratio incentive/disincentive, a lot represents one day of...

  • Ico checkbox

    Paving includes integrant curb and gutter and curb and gutter placed with the same mixture as pav...

  • Ico checkbox

    A change in mix design requires beginning a new lot.

  • Ico checkbox

    Changes in mix design for small quantities such as hand work and high early mixes greater than 35...

  • Ico checkbox

    All samples for testing are taken in a random manner according to the prescribed sampling rate.

  • Ico checkbox

    A minimum of 2 tests and a maximum of 4 tests are required per day.

  • Ico checkbox

    Gradation testing is not required when production is less than 250 cubic meters (cubic yards) per...

  • Ico checkbox

    If less than 3 sublots are produced in a day before the new mix design is initiated, the sublots ...

  • Ico checkbox

    On the first day of production or whenever the mix design is changed prior to the production of 3...

  • Ico checkbox

    On the last day of paving or on the last day of using a specific mix design, the concrete involve...

  • ...and More!

Related Construction, Repair & Improvement Apps... and they're all free for GoCanvas subscribers!

App Name

NRMCA Guideline: Human Resources

The NRMCA Guideline: Human Resources mobile app provides an easy to follow checklist for the following areas: General, Com...

App Name

Cal Trans Asphalt Concrete Plant Insp...

The purpose of Cal Trans Asphalt Concrete Plant Inspection: Continuous Mixing Plant Storage Bins and Cold Feed Systems mo...

App Name

NRMCA Guideline: Measurement, Analysi...

The NRMCA Guideline: Measurement, Analysis and Improvement mobile app provides an easy to follow checklist for the followi...

App Name

Cal Trans Asphalt Concrete Plant Insp...

The purpose of Cal Trans Asphalt Concrete Plant Inspection: Continuous Mixing Plant Weighbelts mobile app is to act as a ...

App Name

NRMCA Guideline: Sample Mix Design Re...

Concrete mix design can entail water-cement ratios, workability, compressive strength and other information about the ceme...

App Name

Portland Cement Concrete: PCC Pavemen...

The Portland Cement Concrete: PCC Pavement Construction Method of Measurement mobile app offers a simple way to manage pav...

App Name

Cal Trans Asphalt Concrete Plant Insp...

The purpose of Cal Cal Trans Asphalt Concrete Plant Inspection: Continuous Mixing Plant Communication mobile app is to act...

App Name

NRMCA Guideline: Sample Report of Job...

The NRMCA Guideline: Sample Report of Jobsite Analysis mobile app is designed to be used for concrete projects. The app re...

More Information